Design of 100 MW LNG Floating Barge Power Plant

Main Article Content

I Made Ariana
Hari Prastowo
Aldio Paruna

Abstract

Floating barge power plant able to supply amount of electricity to undeveloped island in Indonesia. In this research, the generator will be use in the power plant is dual-fuel engine. The process was determine the engine and every equipment along with its configuration then arrange the equipment. The result, MAN18V51/60DF selected along with its system configuration and its general arrangement. The final design enable 7.06 days of operation with daily average load (64.76 MW) or 4.57 days with continues 100 MW load. In the end, the mobile power plant can be built on Damen B32SPo9832 Barge and comply with the regulation.

Article Details

How to Cite
Ariana, I. M., Prastowo, H., & Paruna, A. (2025). Design of 100 MW LNG Floating Barge Power Plant. International Journal of Marine Engineering Innovation and Research, 1(3), 120–127. https://doi.org/10.12962/j25481479.v1i3
Section
Articles